PE板材的安装方法及物料运送
PE板材物料运送方法:
1、安全绳通过硐顶滑轮,把安全绳一端固定距仓口1m左右的一根地锚杆上,另一头绑扎Φ8mm的S型钢筋钩以备施工人员安全的把料运送到下方使用。 PE板、PE棒材 http://www.pebancai888.com
2、板材距边缘150mm处用电钻打孔,再用S型钢筋钩挂入板孔,一人在仓口上方处扶好裁出来的板块,另一人拉住绳子慢慢的把料送入仓内(物料一次性不得超过25公斤)。纪念钞、纪念币 http://www.58sc.com.cn/
PE板材安装方法:
1、超高分子PE板材到货后应查看出厂检验报告,检查板面是否平整,核对材料各项指标是否符合技术规范要求。
2、内壁应清理粘在仓壁上的物料并修复平整,保证PE板与内壁贴实,不得有翘起现象,安装时从下向上依次安装。
3、内壁采用特制的膨胀螺栓固定,先用Φ14mm钻头钻通孔,再用Φ22mm的钻头扩孔,采用m12X150的特制膨胀螺栓固定。
4、螺栓布局按10—15条/m2,在受冲击较大的区域可以增加螺栓固定。
5、为了考虑板材的螺栓系数,在安装时应考虑膨胀间隙,应将竖缝间隙在4mm-8mm之间。
6、先施工煤仓的最下部分,每施工2-3层后,往下放入适量的煤量,然后再施工2-3层,依次重复的施工,直到施工指定的高度。 |